GATE | Gate IT 2007 | Question 52
Consider the CPM activity chart where an arc connecting two milestones is labeled with a task identifier and the time taken in days. For example in order to go from A to B, task T1 takes 180 days. A dashed line depicts an additional dependency that is equivalent to a zero time task.
The set of activities that lie on the critical path are
(A) T1, T2, T8, T10
(B) T1, T3, T8, T10
(C) T1, T2, T3, T4, T5, T6, T7, T8, T9, T10
(D) T1, T4, T5, T7, T8, T10
Answer: (D)
Explanation: Critical path is the one which takes longest time,