GATE | GATE-CS-2016 (Set 1) | Question 24
Given the intervals [(1, 4), (3, 6), (5, 7), (8, 9)], what would be the output of calling a function that solves the Job Scheduling Algorithm?
(A)
[(1, 4), (5, 7), (8, 9)]
(B)
[(1, 4), (3, 6), (8, 9)]
(C)
[(1, 4), (3, 6)]
(D)
[(1, 4), (3, 6), (5, 7)]
Answer: (C)
Explanation: